*Workday Adaptive (for Budget) will be implemented in Fall 2026*
Project Implementation Phases
January 2025 - May 2025
Project team members, with input from key stakeholders, will design foundational elements for the Workday Implementation, including business process redesign for key processes. These will be identified collaboratively by plotting the processes in terms of complexity (number of steps) and the greatest potential for process improvement. Additionally, the project team will engage in a broad range of preparatory activities around project management, change management, initial review and analysis of the HCM and Finance data and an inventory of integrations.
Who's Involved?
Project Leadership Team
Core Team Members
Workstream Leads
Subject Matter Experts
March 2025 - September 2025
Huron will lead NJIT through the review of leading higher education future state process designs, and design confirmation sessions for each functional area. The Huron team will configure the application to match the determined designs, and NJIT will unit test the application to iterate to a final design. The NJIT and Huron teams will also design and build reports and integrations and will begin to convert data from legacy systems. During this phase, change impacts will be identified, the end user training plan will be developed, and the testing strategy will be created.
Who's Involved?
Project Leadership Team
Core Team Members
Workstream Leads
Subject Matter Experts
October 2025 - May 2026
Members of the project team and other stakeholders across campus will conduct end-to-end testing to validate the configured system, integrations and reports to meet user requirements. The Change Management Team will develop and begin to deliver end user training specific to the organization’s needs.
Who's Involved?
Project Leadership Team
Core Team Members
Workstream Leads
Subject Matter Experts
Array of university users
May 2026 - June 2026
The project team will convert all the configuration and data into the production environment. End-user training will continue to be delivered to targeted stakeholders.
Who's Involved?
Project Leadership Team
Core Team Members
Workstream Leads
Subject Matter Experts
Array of university users
July 2026 - August 2026
Technical and functional support will be provided by the Huron team along with the NJIT post production support team. After 3 months the NJIT post production team will take on responsibility.